Non-Material Change One consented

06/04/2021

Non-Material Change Application to East Anglia THREE

In March 2019 East Anglia THREE Limited submitted an application for a non-material change to its planning consent, to the Department for Business, Energy and Industrial Strategy (BEIS) which was consented in June 2019.

The application was to increase the maximum generating capacity from 1,200MW to 1,400MW and to limit the maximum number of gravity base foundations to 100.

In June 2019 BEIS authorised the proposed change application and issued an Amendments Order.