This page provides updates and information on activity for the East Anglia THREE project.
Using a mix of news updates and an interactive map, our aim is to provide clear information on the progress of this project throughout the pre-enabling and construction phase.
Project Activity Map
The East Anglia THREE Project Activity map below provides information on elements of the project and where location specific pre-enabling and construction activity is taking place. You can change your view of the map and the elements of the project that are shown by zooming in and out and selecting different layers. By clicking on the dot icons, you can see information on specific enabling and construction activity by date and time, and type of work. To help you navigate the map, we have provided both a written guide and a video guide, links to which are provided below:
Activity Schedule
The table below lists current and planned pre-enabling and construction works. It also provides information on works that cannot be displayed on the above map as they are not location specific. Please note these are indicative dates and subject to change.
Location | Type Of Work | Description | Start Date | End Date |
---|
Convertor station | Installation of electrical equipment | Consent has been granted for extended working hours from 2 September to 20 December 2024 for the installation of electrical equipment at the converter station site, Bullen Lane. Work can continue within the buildings until 2200, Monday to Saturday.Additional hours have also been granted for Sunday working from 0700 to 1600 on 3 November, 17 November, 1 December and 15 December.Work on the converter station is expected to conclude at the end of 2025/early 2026. | 2 Sept 2024 | 20 Dec 2024 |
Onshore cable route | Fence installation | Temporary fencing of the working area. | Spring 2024 | Autumn 2024 |
Onshore cable route | Access and haul road installation | Installation of temporary access points off the highway and haul road to the working area. | Spring 2024 | Autumn 2024 |
Onshore cable route | Duct proofing | Contractors will be opening up the pre-installed ducts which were laid during the construction of East Anglia ONE. The ducts will be inspected for any remedial action ahead of the cable installation works. | Autumn 2024 | Early 2025 |
Get in Touch
If you have any questions you can get in touch with our stakeholder team on the below email address.
eastangliathree@scottishpower.com
Register below to receive email updates on the project and local activity as it takes place.
For information on other development projects in the area please visit the websites listed below: