Skip to main content
ScottishPower | Iberdrola.com

Select Language:

East Anglia THREE

East Anglia THREE is the second of our East Anglia offshore windfarm projects to be developed and part of the East Anglia Hub. Consent for the project was received on 7 August 2017 and construction commenced in July 2022.

Infographic_East_Anglia_Three

The Project

East Anglia THREE comprises an offshore windfarm approximately 69km from the Suffolk coast and an onshore cable route to transport energy to a convertor station in Bramford. The project includes:

  • An offshore windfarm area of approximately 305km2
  • East Anglia Offshore Wind turbines and associated foundations anticipated to be up to 100 wind turbines
  • From 262m tip height of the turbines and rotor diameter of from 230m
  • One offshore converter station
  • Up to four subsea export cables to transmit electricity from the offshore platforms to shore
  • Landfall at Bawdsey with onshore transition pits to join the offshore and onshore cables
  • Two electrical and up to three fibre optic onshore underground cables, pulled through existing ducting laid by East Anglia ONE, running over 37 km from landfall to the connection point at Bramford
  • An onshore converter station at Bramford, to connect the offshore windfarm to the existing National Grid Bramford substation

Once constructed, the windfarm would operate for up to 25 years.

 

Activity in your area

Activity in your area

Read updates to see what enabling and construction activity is taking place in your area.

Find out more
Document library

Document library

Read all historic and current documentation on the project.

Read more
Contact us

Contact us

Get in touch with our Stakeholder Team with any questions that you have, and register your details to keep updated on the project. 

Get in touch

Background

The East Anglia THREE project, which is wholly owned by ScottishPower Renewables, is the second of our four East Anglia projects to be developed. 

Public engagement on the project began in November 2012, with a series of public consultation activities taking place between 2013 and 2015. An application for development consent was submitted to the Planning Inspectorate in November 2015.

Following application acceptance in December 2015, an examination of the project commenced in June 2016, concluding on 28th December 2016. 

On 28th March 2017 the Planning Inspectorate issued a report of recommendation to the Secretary of State for Business, Energy and Industrial Strategy (BEIS) on East Anglia THREE. The Secretary of State approved the application for consent on 7th August 2017.

In June 2019 BEIS approved a Non-Material Change to increase the overall capacity of the windfarm to 1,400 megawatts (MW). 

In April 2021 BEIS approved a second Non-Material Change to reduce the number of offshore substations to one and to decrease the number of wind turbines and increase their hub height and rotor radius.

In August 2021 a third Non-Material Change was submitted to remove the maximum generating capacity of 1,400MW and to decrease the number of wind turbines and increase their height and rotor radius. This application is currently in the determination phase.

Onshore construction began in July 2022.

Back to top

Footer