Current Progress

Read more about the current progress we are making to construct our €1.4 billion Wikinger Offshore Windfarm.

Wikinger Project Update

Travel offshore with our project team to learn more about Iberdrola's €1.4bn project in the German Baltic Sea. 

 

 

Wikinger Half-Way

Wikinger Half-Way

The installation programme at Wikinger offshore windfarm has passed the half-way milestone with more than 35 of the 70 wind turbines now installed.

Turbine Load-Out

Turbine Load-Out

With all of the jacket foundations now in place, Wikinger's first turbines are loaded on to the installation vessel 'Brave Tern'.

Piling Completed

Piling Completed

The installation vessel 'Giant 7' has now concluded the pile driving works for all 70 turbine locations. Installation of the foundation jackets will also be completed in the coming days ready for turbine installation to commence early next year.
 



 

 

Construction Progress Update - October 2016

See how construction of Wikinger Offshore Windfarm is progressing:

Delivery of first jackets for Wikinger

NAVANTIA and IBERDROLA mark delivery of first jackets for Wikinger

IBERDROLA and Navantia held an event recently to mark the delivery of the first ‘jacket’ foundations for Wikinger offshore windfarm at the Fene shipyard where they were built by a consortium set up by Navantia and Windar. View the press release.

50 Hertz announce start of works for Wikinger export cable

50 Hertz announce start of works for Wikinger export cable

50 Hertz, jointly with National Water Police Office of Mecklenburg-Vorpommern, recently published an information leaflet about the Offshore Cable Project Ostwind 1. It announced the start of the construction works in Mid-May 2016 and provided information around the special conditions and recommendations for commercial shipping, fishing industry as well as for water sports (please note the leaflet is only available in German).

Autumn 2015

Autumn 2015

It is an exciting time for the Wikinger project as major component fabrication has begun. The first A-frame for the foundations is complete and the wind turbine nacelle and blade manufacturing is beginning. Work on the Offshore Substation frame is also complete with the internal fit-out due to commence shortly. We are also beginning to establish our site office at the Port of Sassnitz.

Substation Piling Completed

Substation Piling Completed

Piling for the Offshore Substation is now complete with 6 piles in place ahead of the installation later this summer. The piles were manufactured by Navantia-Tecade and shipped from Sevilla, Spain. Each measures 50 metres in length and weighs 266 tonnes.

Engineering

Engineering

Conceptual and detail engineering has been under development since 2013, with all outputs now officially certified.

Export Cable

Export Cable

The export cable is under the responsibility of 50hertz, the Transmission System Operator. The cable is consented and preliminary works have begun with the objective of connecting Wikinger Offshore Windfarm to the grid in 2017.

Pile Testing

Pile Testing

A pile testing campaign was developed in 2014 in order to improve the design of the turbine’s jacket foundations. As a result of the campaign, very good knowledge about the soil conditions across the site’s sea bed has been achieved.

UXO Campaign

Unexploded Ordnance Campaign

During summer 2015 an unexploded ordnance campaign has been under development in order to minimise any potential risks during the construction phase.

Supplier Event

Supplier Event

In October 2015, we hosted a Supplier Day event at the Landesvertretung Mecklenburg-Vorpommern in Berlin to introduce local companies experienced in offshore wind with our main contractors; Adwen, Navantia, Offshore WindForce and Prysmian.

Christian Pegel, Minister for Energy, Infrastructure and Regional Development for Mecklenburg-Vorpommern, the local Chamber of Commerce and the German Wind Energy Network supported this event and we were pleased to see more than 100 companies engage directly with our contractors to explore possible collaboration opportunities.

Opportunities may exist in a wide range of areas from civil and electrical contractors, vessels and ports support, to technicians and logistics, which will have an overall positive impact on the regional economy. With the manufacture of the offshore substation, foundations and wind turbine rotors already underway, this event was well-timed to capture these requirements and provide local suppliers with the contacts needed to take forward discussions.

 